cooling: 1) cover - hoses to distribution: Technician 2) inner heat screen - installation of distribution, hoses, and leak test 3) pressure relief valve - install, with plug for pressure sensors, hoses 4) leak and pressure test (up to 300 mbar) for all sectors 5) order NPT adapters for pressure relief valves, 14.12. delivery 6) check mounting scheme of pressure relief valve/sensor 7) leak hunting: Rainer FEC: 1) change FEC A05, check electronics 2) A00 und A13, check electronics 3) Wiener test cabling: 1) C12 gating test 2) connect patch panel cables (cover, edge) Rainer, Joachim 3) redo skirt cable routing and testing: Toni 4) storage and fixation of cable rolls: Rainer, technicians 5) CAN-ELMB cable: replace with shielded: Rainer 6) ELMB adapter resistor: Joachim, Marco 7) connector at bretelle display: Thomas misc: 1) ITS-rails 2) ITS cameras: