ALICE TPC, Technical Coordination

Last update of this page 17.02.06


CERN 163426

Installation activities

Minutes of weekly meetings
Daily comments
Schedule mpp pdf (includes grafics) html
Done: 17.2.: FEC installed on A-side except sector 13
Next activities:
Start FEE installation on C-side 22.2.06

Document folder for easy download, date check

Some pictures

TPC Action items

responsiblestatus
DCS with CERN stock ethernet cable:
ok up to 60 m
KIP done
DCS ethernet lines:
check L<60 m
Rainer open
Production of seals for ROC Rudi/Danieldone
design of beam line valve and pump supportDiego, Larsattachment points welded to SSW,
additional SF support point done.
Laser: choice of ccd-camera systemBorgedone
Procurement of non-magnetic force gages for bretelles Peter Gdelivered, at CERN
Bretelles: attachment to feet, bretelles proper Danielstarted
Attachment pieces for ITS services Luciano S., Danieltested
Final feet for SSW Danieldone, in use
Tool for manipulating SSW on crane Danieldone, certified
Welding of supports for tie-rods to space frame Wernerdone
Inner heat screenJoachiminstallation started
Outer heat screenJoachim, Rudi, Danielstarted

Mail: Peter Glässel